Case Study: NHS Healthcare
Completed: March 2022
Client: Wardens Construction
Sector: NHS Healthcare
Budget: £75,000
Services Used
- EV Network Design
- Site Management
- Charge Point & Ground works
- Call strip alarm system
Electric fleet charging for NHS Trusts
Site
Stepping Hill Hospital services people from Stockport and the High Peak. The project transformed an area of the hospital near the laundry into a large EV parking/charging facility for use by the Stockport NHS Trust Estate’s internal vehicles.
Project Outline:
Stockport NHS Trust is committed to achieving a carbon-neutral status by 2040. Our brief was to create EV charge points in dedicated parking bays for use by the Stockport NHS Trust Estate’s internal vehicles.
Project Process:
During meetings with the client, we considered all options to use the available power supply and designed a solution to supply up to twenty-four charge points.
We also considered the traffic flow in the proposed charging bay area and that part of the hospital grounds, the design needed to accommodate the movement and charging of both cars, small, large, and long-backed vans.
We demonstrated how we could design the power load through a ‘back-office’ system, enabling effective vehicle charging within the allotted time schedules required.
The available power is distributed automatically and dynamically between the charge units using dynamic load balancing, enabling the EV charge units to utilise all available electrical capacity from the building.
All connected Fleet vehicles can be charged simultaneously or via a schedule.
EV Chargers for Fleet Solutions:
We chose to use charging units manufactured by EO because of their durability and track record in delivering a charging solution tailored for fleet operations.
We created a secure charging network only available for approved vehicles within the fleet; the back-office suite monitors all usage consumption with detailed reporting.
Project Challenges:
The site is part of a busy hospital, so we worked closely with the NHS Trust and Capital Project Manager to ensure our progressing work did not disrupt the working of the hospital.
Secure EV chargers for fleet solutions
We chose to use charging units manufactured by EO because of their durability and track record in delivering a charging solution tailored for fleet operations.
Secure EV chargers for fleet solutions
We chose to use charging units manufactured by EO because of their durability and track record in delivering a charging solution tailored for fleet operations.
Secure EV chargers for fleet solutions
We chose to use charging units manufactured by EO because of their durability and track record in delivering a charging solution tailored for fleet operations.
The Results
A system designed for easy future growth giving a capacity for 24x 7.4KW charge points (type 2 charging).
Client feedback:
The installation of charge points to support our growing electrical fleet is an essential part of our Green Plan to become a carbon-neutral Trust.
We want to reduce pollution, improve sustainability and help the NHS reach its goal of becoming the first health service in the world to achieve Net-Zero.
Stockport NHS Trust now has the infrastructure to charge twenty-four internal vehicles.
The system is very well designed, and the installation and handover went smoothly.
Wayne Barron
Capital Projects Manager
Stockport NHS Trust